Phase 1
Site preparation and permitting until 31.03.2024.
Phase 2
Construction and installation from 31.03.2024. to 31.07.2024.
Phase 3
Testing and commissioning from 31.07.2024. to 15.08.2024.
Phase 4
Operational phase from 01.09.2024.